Road closures will continue to be updated as construction progresses. Please note that timelines are general and may vary due to weather conditions and unforeseen circumstances. Stay informed for the latest updates to plan your travels accordingly. Thank you for your understanding and patience during this time.

Phase 01A will begin June 23, 2025. This will close the eastbound lanes of Anderson Avenue from Connecticut Avenue to just past College Heights Road. This will continue the road closures at Rebecca Road, Woodland Street, Sycamore Lane, College Heights Road, and Timberlane Drive. 

​

The two west bound lanes will be open for one lane through traffic. 

Community Impacts

The highlighted properties will be impacted daily by this construction project, necessitating the use of alternate roads for residents. Thank you for your understanding and cooperation as we strive to improve the area.

Phase 01
Screenshot 2025-04-02 123656.png
Phase 04 - Connecticut Avenue

Construction Schedule

Providing a construction schedule can help the community understand the duration of closures and potential future impacts on your routine. While schedules can be challenging to predict, they serve as valuable roadmap for our progress and direction. 